Posts

In a group. X men work an efficiency E, men work with efficiency 4E. The group complete Job- A in 13 days in which total effort required was 10001E man-days. In another group X men work with efficiency 2E and Y man work with efficiency 5E. This group completed job-B in 16 days and total effort was 1793E man-days. How long will (4X+3) men working at efficiency E and (Y+9) me working at efficiency 2E take to complete both job A and Job-B?